Meeting with
Shri Ravi Das

Engineer-in-Chief
Municipal Corporation of Delhi
on January 24, 2006 at Ambedkar Stadium, New Delhi

Agenda of the Meeting

Minutes of the Meeting issued from the office of Engineer-in-Chief

 






 

Agenda for the meeting with
Shri Ravi Das
Engineer-in-Chief
Municipal Corporation of Delhi
on January 24, 2006 at Ambedkar Stadium, New Delhi

Agenda of the Meeting

1. Construction of Grade Separator at the junction of Pankha Road and Palam Dabri Road

EE - XX

2. Grade Separator at Kribi Place crossing on Station Road / Jail Road in West Zone

EE - XX

3. Exploring the possibility of Grade Separator at Sagar Pur Crossing

EE - XX

4. Construction of remaining portion of the drain A2A Block, Janak Puri

EE (P) WZ

5. Construction of Wedding Mart - A4A Block, Janak Puri,

EE (P) WZ

6. Improvement of Nallah in C3 & C3A Block of Janak Puri

EE (P) WZ

7. Improvement of Nallah in A1A & A1B Blocks adjacent to Arya Samaj

EE (P) WZ

8. Construction of Poly Clinic at Old Uttam Nagar, MCD Pry. School

EE (P) WZ

9. Construction of Poly Clinic at M-Block, Uttam Nagar

EE (P) WZ

10. Construction of Nallah at A4C Block, Janak Puri

EE (P) WZ

11. Copy of the work orders of various head of MCD (Plan, Non Plan & Councillor Head) & present status of All works.

EE - XXIII

12. Dence Carpet in Flated Area A1A, A1B, C1A, C2A Pkt 15-16, C2B, C2D, C2C Pkt-2, C2C Pkt-12, A4C

EE-XXIII

13. Construction of Library - Possangipur

EE - XXIII

14. Construction of senior Citizen Recreation Centre

EE - XXIII

MUNICIPAL CORPORATION OF DELHI
OFFICE OF THE ENGINEER-IN-CHIEF
TOWN HALL : DELHI-6

No. F507/E-in-C/2006/PA-I                                                    Dated : 1-2-06

A meeting was held in the chamber of the undersigned on 25.01.06 with Shri Sanjay Puri, Municipal Councillor along with Sr. Officers of the MCD along with Chief Engineer-V. The point wise decisions taken are as under :

1. Construction of Grade Separator at the junction of Pankha Road and Palam Dabri Road : It has been decided that a meeting is likely to be organized in the Chamber of Hon'ble Minister Dr. Walia wherein the increase in cost for grade separator project will be decided. This increase in cost is mainly on account of covering of Pankha Road Drain.

2. Grade separator at Kirbi Place crossing on Statio Road/ Jail Road in West Zone : Shri Puri emphasized that he will pursue with Shri Walia for holding a meeting regarding construction of this grade separator. A meeting in this regard be organized in this regard with cantonment/army authorities to resolve the issue.

3. Exploring the possibility of Grade Separator at Sagar Pur Crossing : Ex. Engineer-XX was asked to carry out the feasibility study for construction of this grade separator at Sagar Pur Crossing immediately.

4. Construction of remaining portion of the drain A2A Block, Janak Puri : It has been promised by the E.E. (Pr. West) that the work of construction of remaining portion of the drain is likely to be started by 1st March, 2006.

5. Construction of Wedding Marg - A4A Block, Janak Puri : E.E. (Project West) is to work out the commercial aspects of this issue and put up detail in NIT immediately.

6. Improvement of Nallah in C-3 & C3A Block, Janak Puri : Permission for call of tenders in anticipation has already been given to the concerned Ex. Engineer. He will pursue and get the works awarded by March end.

7. Improvement of nallah in A1A & A1B Blocks adjacent to Arya Samaj : It may be ensured by the E.E. concerned that the inauguration in repspect of this item is held on 3rd Feb. 06.

8. & 9. Construction of Poly Clinics at Old Uttam Nagar MCD Pry. School and M Block Uttam Nagar : E.E. (Pr. West) will ensure that the work of these projects are awarded before June 2006 so that foundation stone may be laid immediately thereafter.

10. Construction of Nallah at A4C Block, Janak Puri : It has been reported by the EE (Pr. West) that the tender for this work has already been received and is in process for award. It should be ensured by EE (Pr. West) that this work is warded by the end of March 06.

11. Copy of the work orders of various head of MC (Plan, Non Plan & Councillor Head) & present status of all works : It was explaind by the concerned Ex. Engineer that some of the works are held up on account of non-availability of the performance guarantee by the contractors. This issue was also discussed in the Standing Committee wherein a decision was taken that the matter would be placed before the Standing Committee for its sppropriate decision through finance, but, the concurrence of finance is still awaited.

12. Dense Carepet in Flated Area A1A, A1B, C1A, C2A Pkt 15-16, C2B, C2D, C2C Pkt-2, C2C Pkt 12, A4C : Budget allocation of Rs. 10 lacks have already been given to the concerned division.

13 & 14. Construction of Library - Possangipur and Construction of Sr. Citizen Recreation Centre : The work of construction of both are in full swing. CE(Elec.) will ensure the work of wiring and electrical installations to be completed before 15th Feb. 06. The inauguration of these buildings will be fixed in due course of time in consultation with the are councillor Shri Sanjay Puri.

The meeting was concluded accordingly.

Sd/-
E.O. to M.E. CUM E-IN-C

DISTRIBUTION :

Chief Engineer-V
S.E. (West)
EE-XV, EE (Pr. West)

Copy to :

Shri Sanjay Puri, Municipal Councilor

Sd/-
E.O. to M.E. CUM E-IN-C



Home | Biography | Vision | Achievements | Social | Business | Letters | Press Releases
Press Clippings
| Janakpuri | Uttam Nagar | Useful Links | Feedback Form | Photo Gallery
Copyright © All Rights Reserved