Meeting
with Shri
Arun Mathur, IAS, CEO, Delhi Jal Board
on 21st June, 2006 at 3:30 p.m. at Varunalaya Phase-II,
Karol Bagh, New Delhi-110005



Agenda
of the Meeting
1.
Progress review of construction of under ground reservoir
adjacent to A5B-A5C Block, Janak Puri.
2.
Progress review of construction of sum well pumping
station in B-Block, Janak Puri.
CEO is requested to monitor booth the above projects
personally on monthly basis so that these projects
can be accomplished in time bound period.
3.
a) The acute drinking water shortage in Janak Puri
and Uttam Nagar group of Colonies. The quantity of
water received by Janak Puri is the same as it was
20 years back. But now the population has increased
manifolds hence more quantity of water is needed for
Janak Puri.
b) Increase of Water level at B-2 Block, Under Ground
Booster Pumping Station Janak Puri
Minimum Level Required - 3.80 m.
Maximum Level Available - 3.00 m.
c) 2 additional Water Connection (10") for A
- Block, Janak Puri (Specially for A-1 Block Kothies
& Flats) and 1 connection for Chanakya Place,
Jeewan Park and Indira Park from South Delhi Main
for proper Water Supply. (Water hardly available for
10-15 minutes at very low pressure).
4.
Problem of sewer over flow in A2 and C2 Block (replacement
of un settled sewer line) Janak Puri.
5.
Laying of sewer lines in left out portion of Uttam
Nagar Group of Colonies namely Ramdutt Enclave, East
Uttam Nagar, Indira Park, Milap Nagar, Dayal Sar Road,
Prem Nagar and South Extn.
6.
Shortage of drinking water and problem of contaminated
water in C-Block, E-Block and F-Block Jeewan Park,
C, D & E Block Chanakya Place, A&D Block East
Uttam Nagar, G-Block Uttam Nagar.
7.
Cleaning of under ground water tank of A1A Block.
8.
Cleaning of sewer line Dist. Centre to Club Road Janak
Puri.
9.
Restoration of musteroll for cleaning of residential
sewer lines before Monsoon.
10.
Replacement of under sized water pipeline in A4C,
A1B, C2 and C3 Block MIG Flats of Janak Puri.
11.
Sewer surcharge / over flow problem in C2D, C2C Pkt-2,
C2A Pkt-15 & 16 and C2B Block in Janak Puri due
to the pardi at C2B Crossing (600 dia metre sewer
line)
12.
C2B Jal Board Office (ZRO) may be instructed to collect
Sewer Development Charges also.
13.
Extension of date of Deposit of Sewer Development
Charges (with rebate) in Uttam Nagar Group of Colonies
upto 30th September, 2006.