Meeting with Shri Haroon Yusuf, Hon'ble Power Minister, Govt. of NCT of Delhi regarding electricity problem related to BSES Rajdhani Power Ltd. in Janak Puri and Uttam Nagar.

 

Summary of Proceedings of Meeting with Shri Sanjay Puri, Councillor (MCD) &
RWA's on 05.09.2005 in the office of Minister (Transport & Power), GNCTD
Chaired by Shri Haroon Yusuf, Minister (Transport & Power), GNCTD

No. F-50/PA/MOTP/Minutes/2005/9607-11                                                             Dated 14-9-05

1. Streetlights

Shri Haroon Yusuf, Minister (Transport & Power) very categorically observed that no negligence in maintenance of streetlights would be tolerated.

BSES officers agreed to attend to the problem of streetlights of Uttam Nagar & Janakpuri within a week.

2. Installation of 66 KV Grid adjacent to Bus Terminus

Spl. Secy. (Power) informed that revised demand not had been issued by DDA on 24/8/2005 for land. He assured that the amount (i.e. 1.55 crore approx) would be deposited very soon and the use of the land would be given to the Discom as per govt. policy for setting up of grid.

Minister (Transport & Power) asked the Discom to take up the project on priority.

3. List of Repair / Maintenance & Augmentation Works

Minister (Transport & Power) was given by Shri Sanjay Puri a list of maintenance and augmentation work (list attached) that needed immediate attention.

Minster (Transport & Power) asked these works to be attended to on priority. BSES officers stated that they would attend to these works and complete them within a month.

4. Many Feeder Boxes in Uttam Nagar & Janak Puri without Cover

Minister (Transport & Power) directed that these be attended to immediately. BSES officers present agreed to replace the dilapidated / coverless feeder boxes.

5. Encroachment outside Indra Park Substion

It was pointed out that this encroachment posed a hzard in the event of emergencies.

Minister (Transport & Power) asked BSES to approach the authorities concerned for necessary action.

6. Mahindra Park Residential Area Substation has no Gate and is a hazard in case children happen to go in.

Minister (Transport & Power) asked this to be attended to immediately and to report compliance within a week.

7. Power Meter

Representatives of RWAs and Councillor expressed their apprehension that the electronic meters were fast. Minister (Transport & Power) observed that a camp should be organized to test the meters and replace the fast meters.

Sd/-       

(ABHIJIT SARKAR)
SECRETARY TO MINISTER
(TRANSPORT & POWER)

Encl. (i) List of participants

       (ii) As in para 3


Home | Biography | Vision | Achievements | Social | Business | Letters | Press Releases
Press Clippings
| Janakpuri | Uttam Nagar | Useful Links | Feedback Form | Photo Gallery
Copyright © All Rights Reserved